3 ongoing2 completed
Maternity Wing Expansion
OngoingInfrastructure

Maternity Wing Expansion

Expansion of the existing maternity unit to increase delivery capacity from 2 to 6 beds. The project includes construction of a new post-natal ward, a newborn care room, and an attached ablution block.

Progress65%
Start: Jan 2025End: Sep 2025Funder: TM Aspire Internal Capital Fund
Milestones
Design & Bill of Quantities approved
Foundation works completed
Superstructure works (walls & roof)
Electrical & plumbing installations
Finishes & fittings
Commissioning & handover
Electronic Medical Records (EMR) Implementation
OngoingDigital Health

Electronic Medical Records (EMR) Implementation

End-to-end digitisation of patient records using an open-source EMR system. This project covers system setup, staff training, data migration, and integration with the laboratory and pharmacy modules.

Progress40%
Start: Mar 2025End: Dec 2025Funder: TM Aspire ICT Budget & Technical Assistance – AMREF
Milestones
System selection & procurement
Server setup & network installation
Pilot deployment in Outpatient
Staff training (clinical & admin)
Full facility rollout
Go-live & support phase
Solar Power Installation
OngoingGreen Energy

Solar Power Installation

Installation of a 15 kWp rooftop solar PV system with battery storage to reduce reliance on grid power and ensure uninterrupted electricity for critical clinical services including the laboratory, pharmacy cold chain and maternity ward.

Progress30%
Start: May 2025End: Aug 2025Funder: TM Aspire Capital & Kenya Power Financing Scheme
Milestones
Site assessment & design completed
Equipment procurement
Structural mounting installation
PV panel & inverter installation
Battery bank connection
Commissioning & grid synchronisation
Laboratory Block Renovation
CompletedInfrastructure

Laboratory Block Renovation

Renovation of the existing laboratory block including new wall and floor tiling, upgrading of electrical sockets and lighting, installation of improved ventilation, and repainting of all surfaces. Completed on schedule.

Progress100%
Start: May 2025End: Jun 2025Funder: TM Aspire Internal Capital Fund
Milestones
Demolition & surface preparation
Tiling – floors and walls
Electrical upgrade
Ventilation installation
Painting and finishes
Handover to laboratory team
Perimeter Fencing & Security Lighting
CompletedSecurity

Perimeter Fencing & Security Lighting

Full perimeter fence installation around the TM Aspire compound using chain-link fencing and concrete posts. Solar-powered floodlights were installed at all four corners and the main entrance to improve security after hours.

Progress100%
Start: Jan 2025End: Feb 2025Funder: TM Aspire Capital Fund
Milestones
Survey & peg out
Post driving & concreting
Chain-link fencing
Gate installation
Solar floodlights
Handover